Keene, NH Airport
Project Statistics
Location: Keene, New Hampshire
Highlights
- Full reconstruction of Taxiway A
- Pavement removal and gravel replacement
- New underdrains and duct bank crossings
- Taxiway edge lighting and pavement markings
- Late-season paving completed using jet dryers to heat and dry the pavement surface
- Base and top lifts achieved PWL scores of 106
- Work coordinated to minimize disruption to airport operations
About the Project
Casella Construction completed a full reconstruction of Taxiway A at Keene Airport, including pavement removal, gravel replacement, underdrains, duct bank crossings, edge lighting, new pavement, and pavement markings.
The compressed project schedule required paving to extend into late November, creating an unusual challenge for meeting FAA requirements that asphalt be placed at 45 degrees and rising. With late-November temperatures below that threshold, two jet dryers were brought in to heat and dry the pavement surface ahead of paving operations.
The approach allowed paving to proceed despite the cold temperatures, with both the base and top lifts exceeding FAA compaction requirements and earning PWL scores of 106. Challenging conditions continued through the final stages of the project, with saw cutting and topsoil placement completed during snowstorms to ensure scheduled flight operations were not disrupted.