115 KV Line Replacement

Project Statistics

Location: Weathersfield, Vermont to Ascutney, Vermont
Completion: Summer 2017
Schedule: CCI completed all right-of-way access construction and earthwork in 12 weeks

Highlights

  • Construction and stabilization of 50 structure pads
  • 63 culverts of various sizes
  • 1,200 cy of rock removal
  • Installation and removal of 3,200 timber mats

About the Project

Casella Construction, Inc. (CCI) was contracted to perform earthwork and install erosion control measures along a 5-mile project designed to completely replace the existing 115 KV line and structures from Weathersfield, Vermont to Ascutney, Vermont.

CCI constructed this project with an aggressive schedule consisting of 3 crews working consecutively along the right-of-way. Work included construction of 4-miles of stone access road, installation and removal of 3,200 timber mats, construction of 50 structure pads, removal of 1,200 cy of rock by hydraulic hammer, installation of 63 culverts, installation and maintenance of 7,000 lf of reinforced silt fence and straw wattle, removal of 84 wood structures, and restoration of the entire right-of-way at the completion of the project.

CCI completed all right-of-way access construction and earthwork in 8 weeks, allowing linework to begin significantly ahead of schedule. All access construction work was performed while the existing 115 KV line was active.

Construction of Stone Access Roads
Construction of Stone Access Roads
Placement of Timber Mats
Placement of Timber Mats