Bennington Peanut Roundabout

Bennington Peanut Roundabout

Project Statistics

Client: Vermont Agency of Transportation
Location: Bennington, Vermont
Date Completed: September, 2026
Contract Value: $6.45 million

Highlights

  • Vermont’s first peanut-style roundabout
  • More than 1,000 feet of drainage pipe installed
  • More than 5,000 cubic yards of dense-grade gravel placed
  • More than 3,000 feet of granite curb installed
  • Approximately 2,000 tons of asphalt placed
  • 14 new lights installed
  • New concrete islands, sidewalks and pedestrian crossings
  • Temporary bypass road constructed to maintain traffic through the project

About the Project

Casella Construction served as the general contractor for Vermont’s first peanut-style roundabout, located at the intersection of VT Route 67A, Silk Road, Matteson Road and College Drive near Bennington College.

The project rebuilt the intersection from the ground up with new drainage, utilities, roadway, granite curbing, concrete islands, sidewalks, lighting and pavement. The new configuration was designed to slow vehicles, simplify traffic flow and improve safety and access for drivers, pedestrians and bicyclists at what had historically been a confusing, high-crash intersection.

To keep traffic moving while providing crews with a safer and more efficient work area, Casella Construction built a temporary bypass road around the primary construction zone. The approach replaced the original seven-phase traffic plan and allowed much of the roundabout to be constructed without routing vehicles directly through the active work area.

Brandon Route 7

Brandon Route 7

Project Statistics

Client: Vermont Agency of Transportation
Location: Brandon, Vermont
Date Completed: July 2021
Value: $23 million

Highlights

  • 1.3 miles of US Route 7 reconstructed through Downtown Brandon
  • 100,000 cubic meters of excavation
  • 2,275 meters of sewer pipe and 49 sewer manholes
  • 3,500 meters of stormwater pipe and 170 catch basins
  • 1,852 meters of water pipe
  • 2,421 meters of utility services
  • 6,600 square meters of sidewalk
  • 76,000 cubic meters of aggregate
  • More than 5,700 daily car and truck trips maintained through the work zone
  • Work coordinated with 158 residences and businesses Brandon

About the Project

Casella Construction was contracted by the Vermont Agency of Transportation to reconstruct 1.3 miles of US Route 7 through Downtown Brandon. The three-year project included new water, sewer, and stormwater systems; primary and secondary electric; site lighting; roadway widening and reconstruction; traffic signals; concrete sidewalks; granite curbing; pavement markings; and signage.

With construction taking place through the center of downtown, traffic flow and coordination with the surrounding community were major considerations throughout the project. More than 5,700 cars and trucks traveled through the work area each day, while work also had to be coordinated with 158 individual residences and businesses.

The project was divided into phases with scheduled milestones to limit disruptions as work progressed through downtown. This allowed the extensive underground utility and roadway reconstruction to move forward while maintaining access for the traveling public, residents, and businesses.