Killington Municipal Water System

Project Statistics

Client: Town of Killington
Location: Killington, Vermont
Date Completed: September 2026

Highlights

  • Approximately 1.8 miles of waterline installed
  • Approximately 1,500 feet of vertical elevation
  • 750,000-gallon water storage tank
  • Two wells and a new pump station
  • Meter vaults and distribution manifolds
  • Slopes exceeding 50 percent in some areas
  • 9,000 tons of pipe-bedding material supplied by Casella Construction’s Clarendon Quarry
  • Extensive rock blasting, retaining-wall construction, drainage work and road restoration

About the Project

Casella Construction completed the infrastructure work for Killington’s new municipal water system, which will support future housing, businesses and development within the resort district.

The project included the installation of wells, transmission mains, a pump station, meter vaults, manifolds and a 750,000-gallon water storage tank. Crews worked across exceptionally steep and challenging terrain, installing the system over approximately 1,500 feet of elevation.

The work also required rock blasting, complex drainage and retaining-wall construction, specialized pipe installation and extensive road restoration. Employees from across Casella Construction contributed to the project over more than two years, with the company’s Clarendon Quarry also supplying pipe-bedding material.